Capacity Planning: Who Has Time for What Next Week

Every week, more is promised than fits into the week. This is rarely due to too little effort, but to a calculation that was never made: how many hours does the team really have, and how many of them are already taken?

Stacked old wooden crates in faded colours
Photo: Rob Sheahan / Unsplash

Key takeaways

  • Only the time left after absences, fixed appointments, and daily business can be planned. In many teams that is less than half of working time.
  • People regularly underestimate when a task will be finished because they ignore interruptions and competing tasks. Research calls this the planning fallacy.
  • Planning close to full utilization creates queues. A buffer is not a convenience but the condition for reliable deadlines.
  • The best yardstick for the next estimate is experience with similar tasks, not the plan for the current one.

Why teams promise more every week than they can deliver

On Monday the week looks good. The quote for the major customer, preparing the trade fair, two customer meetings, the new price list. By Friday two of them are done, the rest has slipped into next week. In between there were calls, a complaint, a colleague out sick, and three questions from the workshop. None of it was unusual, and yet none of it was in the plan.

If this keeps happening, promises lose their value. Customers hear “next week” and count on the week after, colleagues plan their work around deadlines that will not hold anyway. This article answers the question: how does a small company plan reliably who has time for what next week? To do so, we clarify the terms, introduce a thinking model from decision research, weigh two views on the accuracy of estimates, and work through a weekly capacity calculation in full.

A plan that allocates every hour has no room left for reality by Monday noon.

What is capacity planning, and which time can actually be planned?

Capacity is the working time a person or team has available in a given period. Capacity planning matches this time with demand: which tasks are pending, how much time do they need, and who takes them on? In a small company, the sensible period is usually the week, because it coincides with the weekly planning described in the article on weekly team planning.

What matters is which time can actually be planned. Vacation, sickness, and fixed appointments come off contractual working time first. Not all of what remains is usable, because breaks, short check-ins, and switching between tasks cost time. The article on how to calculate process costs sets this practical capacity at around 80 percent. And finally there is a base load: daily business that comes up every week without anyone planning it, such as inquiries, complaints, and questions. Only what is left after that is free for projects and initiatives.

From working time to plannable project time for one person in one week
  1. 40Contractual working time
  2. 36After fixed appointments90% of previous stage
  3. 29Practically usable (80 percent)81% of previous stage
  4. 17After base load of daily business59% of previous stage

Worked example with freely chosen numbers: four hours of fixed appointments, twelve hours of base load from the average of recent weeks. Of 40 hours, 17 can be planned for initiatives.

The number at the end surprises many owners. But it explains why a plan that assigns 35 hours of project work to one person cannot hold. The base load cannot be estimated, it has to be read from the past, for example from a ticket system as described in the article on bundling customer inquiries, or from one week of time records.

The thinking model: the planning fallacy

In 1979, Kahneman and Tversky described a tendency they called the planning fallacy. People underestimate the time they need for an upcoming task even though they know that similar tasks took longer in the past. The cause lies in how planning is done. Whoever estimates imagines the path from start to finish, and that image is idealized. Interruptions, questions, and competing tasks hardly appear in it.

Wiese, Buehler, and Griffin (2016) highlight a distinction that is central to capacity planning. Performance time is the time someone actually spends working on a task. Completion time is the point at which the task is finished. Between the two lie other tasks, interruptions, and waiting times. According to research, estimates of completion time are considerably more prone to optimism than estimates of performance time. Whoever says “That takes four hours” may well be right. Whoever turns that into “That will be done tomorrow” often is not.

An analogy makes this tangible. According to the navigation system, the drive to the customer takes 40 minutes. Anyone who wants to be on time still leaves an hour earlier, knowing that refueling, looking for parking, and the traffic jam on the arterial road are not included in the 40 minutes. For office tasks this experience is often missing, because nobody records how long things really took.

What research shows about better estimates

In four experiments, Wiese, Buehler, and Griffin (2016) tested a method often recommended in project practice: backward planning. You start at the target date and go through the necessary steps in reverse order back to today. Participants who planned backward predicted longer completion times in all four studies than those who planned forward or without instructions. In the fourth study, where the prediction could be compared with the actual result, these predictions were less biased. Backward planning drew more attention to obstacles, interruptions, and competing demands.

In their introduction, the authors also summarize earlier findings. People who are asked to explicitly recall earlier completion times estimate less optimistically. In large construction projects, so-called reference class forecasting reduces time and cost overruns. It aligns the estimate with the actual results of comparable earlier projects rather than with one's own plan. Breaking a task into sub-steps, by contrast, showed mixed results and can even increase optimism when a very detailed plan creates a false sense of certainty. Buehler, Griffin, Lam, and Deslauriers (2012) also found in four studies that participants who imagined a task from an observer's perspective predicted longer and therefore less biased completion times. They paid more attention to possible obstacles.

4experiments on backward planning
3planning directions tested: backward, forward, unspecified
4studies on the observer perspective by Buehler et al.

Source: Wiese, Buehler, Griffin (2016); Buehler et al. (2012)

Two views: do we always underestimate?

The first view is: estimates are fundamentally too optimistic, so every estimate should be increased across the board. The broad research on the planning fallacy supports this.

The second view disagrees. Thomas, Newstead, and Handley (2003) found no underestimation but an overestimation of duration for a simple, clearly structured task. Those who had done the task before estimated more accurately. The authors suspect that the duration of the task plays a major role: for short, simple tasks people tend to overestimate the time.

Both findings can be reconciled, and a useful rule follows. Short routine tasks that the team knows tend to be estimated generously and need no markup. Longer, new, or dependent tasks are underestimated, above all regarding when they will be finished. For these, looking at earlier similar cases is worthwhile. A flat markup on everything is therefore less accurate than distinguishing by type of task.

Which tasks tend to be under- and which overestimated
Type of taskTypical tendencyWhat helps
Short, familiar, no dependenciestends to be overestimatedaccept the estimate, no markup
Longer, familiarcompletion underestimatedlook at the duration of the last three similar cases
New or one-offclearly underestimatedplan backward, name obstacles explicitly
Dependent on customers or supplierscompletion strongly underestimatedplan waiting time separately, not as working time

Why full utilization destroys deadlines

A second reason for missed deadlines has nothing to do with estimates. It lies in utilization. Queueing theory, a branch of mathematics, describes what happens when tasks arrive irregularly and take different amounts of time. The closer utilization gets to 100 percent, the faster waiting times grow, and not evenly but ever more steeply.

Average waiting time of a new task relative to its processing time, by utilization
  • 50 percent utilization1 ×
  • 70 percent2.3 ×
  • 80 percent4 ×
  • 90 percent9 ×
  • 95 percent19 ×

Worked example based on the simplest queueing model with random arrivals and random durations: waiting time = utilization divided by (1 minus utilization). Real teams deviate from this, but the shape of the curve remains.

At 80 percent utilization, a new task waits on average four times as long as its processing takes. At 95 percent, already nineteen times. For a customer waiting for a quote, that is the difference between two days and two weeks. It follows that a buffer in weekly planning is not a convenience but the precondition for urgent work to find room at all. Limiting parallel work, as described in the article on OKR, Kanban, and weekly planning, works in the same direction.

How to plan capacity for next week

  1. Available hours per person

    Subtract vacation, sickness, and fixed appointments from working time. Take 80 percent of the rest as practically usable.

  2. Subtract the base load

    Subtract the average daily business of the last four weeks. Without measurement, start with a third of usable time and correct it after the first weeks.

  3. Estimate initiatives

    Estimate the performance time for each initiative. For longer or new tasks, look at how long the last similar ones took, and plan backward from the deadline.

  4. Allocate only up to plannable time

    Allocate initiatives only up to each person's plannable time. Whatever does not fit is postponed or handed off, and on Monday, not on Friday.

  5. Compare plan and actual on Friday

    Note for each initiative how long it actually took. This list is the reference class for the next estimate.

The last step is the most important and the one most often skipped. After a few weeks, the team has its own collection of actual durations that improves every estimate. When initiatives no longer fit into the week, that is not a planning error but information for a decision: postpone, hand off, or drop something else. The article on how to delegate tasks describes handing off with a clear handover. For larger initiatives with several people involved, the article on planning projects in small teams helps.

Conclusion: how does a small company plan reliably?

The question was  a small company plans reliably who has time for what next week. The answer consists of three honest calculations. First, only the time left after appointments, breaks, and daily business counts, and that is often less than half of working time. Second, longer and new tasks are underestimated above all regarding when they will be finished, and looking at earlier similar cases helps more against this than a flat markup. Third, every plan needs a buffer, because full utilization lengthens waiting times disproportionately. Planning does not become reliable through more detailed plans but through the weekly comparison of plan and actual.

What you can put into practice right away

  1. Calculate each team member's plannable time for next week: working time minus appointments, 80 percent of that, minus base load.
  2. Place the planned initiatives next to it and check where more is assigned than can be planned.
  3. Decide on Monday what gets postponed or handed off.
  4. On Friday, have the actual duration noted for each initiative.
  5. Repeat this for four weeks and use the list of actual durations for the next estimates.

After four weeks you will know how large the base load in your team really is and how far estimates and results diverge. With these two numbers, promises to customers become reliable again.

Frequently asked questions

What is capacity planning?

Capacity planning matches a team's available working time with demand: which tasks are pending, how much time they need, and who takes them on. In small companies it is usually done weekly, together with weekly planning.

How do you calculate an employee's available capacity?

Vacation, sickness, and fixed appointments are subtracted from working time. Around 80 percent of the rest counts as practically usable. Subtracting regular daily business leaves the time that can be planned for projects and initiatives.

What is the planning fallacy?

The planning fallacy, described by Kahneman and Tversky (1979), is the tendency to underestimate the time for an upcoming task even though similar tasks took longer in the past. It mainly affects the question of when a task will be finished, because interruptions and other tasks are ignored.

How much buffer should you plan?

There is no fixed number. Queueing theory shows, however, that waiting times rise sharply above 80 percent utilization. Anyone who wants to handle urgent work reliably should not allocate all plannable time.

How do time estimates become more accurate?

The most effective approach is to look at the actual duration of earlier similar tasks. In experiments, planning backward from the target date also led to more realistic predictions. Short routine tasks, by contrast, tend to be overestimated and need no markup.

Sources

  1. Wiese, J.; Buehler, R.; Griffin, D. (2016): Backward planning: Effects of planning direction on predictions of task completion time. Judgment and Decision Making, 11(2), 147-167.
  2. Kahneman, D.; Tversky, A. (1979): Intuitive prediction: Biases and corrective procedures. TIMS Studies in Management Science, 12, 313-327.
  3. Thomas, K. E.; Newstead, S. E.; Handley, S. J. (2003): Exploring the time prediction process: the effects of task experience and complexity on prediction accuracy. Applied Cognitive Psychology, 17(6), 655-673.
  4. Buehler, R.; Griffin, D.; Lam, K. C. H.; Deslauriers, J. (2012): Perspectives on prediction: Does third-person imagery improve task completion estimates? Organizational Behavior and Human Decision Processes, 117(1), 138-149.

All sources in the knowledge base

Reading room of a historic library with galleries, walls of books, and a skylight

Found a mistake or a topic that’s missing?